Artesian Park
Clinton, MO
White INTER-GLASS Interior and tiled racing lanes
PROJECT ASSESSMENT
The pool was originally built in 1968 and no major renovations had been completed since then! The city had an annual budget for paint, but it was not large enough to buy enough paint for the whole pool. Each year they would repaint different sections of the pool, resulting in layers and layers of paint. Over the years, the pool surface became incredibly rough and some cracks had appeared. The walls were worn down and had developed porous holes, making it almost like coral in places. The city was ready to hang up their paintbrushes and find a long-lasting solution!
RENOVATION PLAN
This project was done from January to May of 2022. The first step was to hydroblast the pool surface to remove all the layers of paint. Next a new concrete wall surface was rendered along one side of the pool as well as a section of the pool floor to make everything flush. Once this was completed, the tiled racing lanes and targets were set. At this point, repairs were made to any significant cracks and finally the INTER-GLASS surface was applied on the floor, walls, and the gutters as well.
PROJECT ASSESSMENT
The pool was originally built in 1968 and no major renovations had been completed since then! The city had an annual budget for paint, but it was not large enough to buy enough paint for the whole pool. Each year they would repaint different sections of the pool, resulting in layers and layers of paint. Over the years, the pool surface became incredibly rough and some cracks had appeared. The walls were worn down and had developed porous holes, making it almost like coral in places. The city was ready to hang up their paintbrushes and find a long-lasting solution!
RENOVATION PLAN
This project was done from January to May of 2022. The first step was to hydroblast the pool surface to remove all the layers of paint. Next a new concrete wall surface was rendered along one side of the pool as well as a section of the pool floor to make everything flush. Once this was completed, the tiled racing lanes and targets were set. At this point, repairs were made to any significant cracks and finally the INTER-GLASS surface was applied on the floor, walls, and the gutters as well.